Bauer constructs cut-off wall for hydroelectric power plant in Nepal
28/03/2022
Pubblicato da Redazione
A Klemm KR 909 is being used for the drilling and injection work by Bauer Engineering India Pvt. Ltd.
The Arun River in Nepal flows from Tibet through the Himalayas into China. Of all Nepalese river basins, it has the largest area covered in snow and ice. A new hydroelectric power plant is currently being constructed on this river, and it is expected to produce up to 900 MW of electricity.
Bauer Engineering India Pvt. Ltd., a subsidiary of Bauer Spezialtiefbau GmbH, was tasked by the Indian company Jaiprakash Associates Limited with the construction of a cut-off wall as part of the project Arun III HEP. The goal is to achieve a seal and reduce seepage water below the upstream cofferdam and in the left and right abutments. The scope of service provided by Bauer includes the execution of 3,500 running meters of drilling and injection work on the cofferdam. In the granular construction soil, composed of sand, gravel, rubble and boulders, the pore injections are executed by means of tube-à-manchette and annular grouting.
“Using the pore injections, we are able to fill the pores in the very loose soil with cement slurry and thereby reduce its permeability”, explains Project Manager Satish Kumar. He continues: “Injections require a high degree of quality assurance and quality control. We are able to meet the strict demands thanks to our many years of experience.” In addition to the pore injections, Bauer will also carry out rock grouting in order to fill gaps, fractures and cavities in the rock. Due to the remote location in the Himalayas, not only the construction soil poses a challenge, but also logistics. On top of that, the schedule is very tight: this is because snow starts to melt in March, causing the water level in the river to rise and making work more difficult.
A Klemm KR 909 is being used for the drilling and injection work. The work executed by Bauer started in December 2021 and is expected to be completed by May 2022.
Ultime notizie di Bauer Macchine Italia
Perforation
30/09/2024
Bauer Spezialtiefbau modernizes John Hart Dam in Canada
Improvement of downstream public safety and facility reliabi...
Perforation
18/07/2024
Bauer secures port project in Scottish town of Ardersier
Bauer constructs diaphragm walls up to 42 m deep and anchor...
Perforation
05/12/2023
Bauer relies on full e-power during Dutch infrastructure project
Innovative electric drill rig from Klemm in operation for th...
Perforation
04/11/2023
Bauer India constructs the deepest diaphragm wall element
Bauer India constructs the deepest diaphragm wall element du...
Perforation
27/10/2023
Klemm Bohrtechnik GmbH celebrates double anniversary
This year, Klemm Bohrtechnik GmbH is celebrating two anniver...
Perforation
26/09/2023
Brownfield Remediation from A to Z on Berlin Airport Grounds
Alongside the operations building, they also needed to disma...
Altri International
International
27/11/2024
Home of Volvo Construction Equipment’s pioneering articulated haulers advances to Climate Efficient Site
As one of the construction industry’s most active drivers of...
International
26/11/2024
Mota-Engil orders 10 Liebherr railroad excavators for a major project in West Africa
The Portuguese construction company Mota-Engil has once agai...
International
25/11/2024
New Grove GMK3060L-1 drives busy schedule for Mann Crane Hire
• Mann Crane Hire selected the GMK3060L-1 for its class-lead...
International
25/11/2024
Prinoth Unveils Expanded Production Facility in Granby, Canada
Prinoth held an event to announce the official opening of it...
International
23/11/2024
GPMat International takes delivery of two Raimondi T147s residential development in the South of France
- Official agent of France expands its product lineup with t...
International
22/11/2024
Sarens acquires additional SCHEUERLE SPMT K24 modules
renowned for its expertise in crane rental services, heavy l...