Bauer involved in construction of Frankfurt residential quarter WESTVILLE

26/08/2021

Pubblicato da Redazione

  • /storage/old/nc6001568/16295292577832.jpeg

BAUER Spezialtiefbau GmbH was commissioned by BST Becker Sanierungstechnik GmbH, on behalf of the owner Instone Real Estate, with the construction of an impermeable mixed-in-place (MIP) retaining wall with a single-layer tie back.

On the west side of the Gallus district of Frankfurt, a residential quarter is being constructed with more than 1,300 apartments, a two-story underground garage, daycare centers as well as commercial and retail units. BAUER Spezialtiefbau GmbH was commissioned by BST Becker Sanierungstechnik GmbH, on behalf of the owner Instone Real Estate, with the construction of an impermeable mixed-in-place (MIP) retaining wall with a single-layer tie back. 

 

Bauer constructs the retaining structure for construction sections WA 5 to WA 7. In total, approximately 12,000 m2 of static retaining wall is being constructed up to a depth of 18 m. “To ensure the possibility of easy dismantling, the top 2 m of the retaining wall is mostly constructed with timber lagging extending approximately 1,200 m2,” explains Bauer Site Manager Arno Schebaum. “For quality assurance of the retaining structure, inclinometer measuring points are set up, anchor load measurement cells are installed and a deformation check is carried out.”

 

In addition, temporary anchors of up to 30 m in length are constructed to tie back the retaining structure. This work involves approximately 5,000 m of drilling. An RG 16 T and an RG 25 S are used for the mixed-in-place work to construct the retaining structure. A KLEMM KR 806 is used for the installation of the anchors. 

 

The advantages of the MIP construction method are the shorter execution time as well as its sustainability, because the building material is produced on site using the existing soil as an aggregate. This significantly reduces not only the delivery time of the materials, but also the time needed for removal of the excavated material and thus the emission of greenhouse gas. 

 

The work executed by Bauer began in February this year and will continue until August 2021. The new residential quarter WESTVILLE on Kleyerstrasse, on the grounds of the former Avaya site, is expected to be completed by mid-2025. 



 

 