Bauer: mixed-in-place cut-off wall for flood protection
18/11/2019
Pubblicato da Redazione
![/storage/old/nc6001066/15738085687345.jpeg](/storage/old/nc6001066/15738085687345.jpeg)
Bauer: mixed-in-place cut-off wall for flood protection
The Rhine is one of the busiest rivers in the world. With a total length of over 1,200 km, it is also the second-longest river in the German-speaking region.
A number of dikes along the Rhine river offer permanent flood protection, including one located in immediate proximity to the Muendelheim district in Duisburg. To give the river more room to expand at high water and thus avoid peak flows, the existing dike at Muendelheim will be relocated, creating approximately 60 ha of retention space.
In preparation for the relocation, a cut-off wall is being constructed along the line of the future dike to protect the adjacent city district from groundwater pressure. The city of Duisburg comissioned Bauer Spezialtiefbau GmbH with the construction of a mixed-inplace (MIP) cut-off wall. In this method, the soil is broken up with a triple auger, shifted, and then mixed with a binder slurry in the resulting bore hole.
"The big advantage of the MIP method is that there is no excavation. The soil doesn't have to be removed from the site; it can be used directly as aggregate. That is a definite plus, especially for the local residents,” says Mike Schwermer, project manager at Bauer Spezialtiefbau. The finished MIP cut-off wall will measure 1.6 km in length. With a width of 550 mm and a depth of up to 20 m, the total volume of the wall will be around 28,000 m3. "The strict quality requirements for the MIP wall pose a particular challenge. It must have exceptional leak tightness and a final rigidity within a specific bandwidth," explains Mike Schwermer. The cut-off wall will be constructed parallel to the Rhine river on the future
route of the dike.
Work on the project began in July 2019 using an RTG RG 25 S with MIP equipment. Bauer plans to complete the cut-off wall in March 2020.
![](/storage/aziende/14849901962775.jpg)
Ultime notizie di Bauer Macchine Italia
Perforation
18/07/2024
Bauer secures port project in Scottish town of Ardersier
Bauer constructs diaphragm walls up to 42 m deep and anchor...
![Bauer relies on full e-power during Dutch infrastructure project](/storage/2023/12/bauer-relies-on-full-e-power-during-dutch-infrastructure-project-656dc6f86eda6.jpg)
Perforation
05/12/2023
Bauer relies on full e-power during Dutch infrastructure project
Innovative electric drill rig from Klemm in operation for th...
![Bauer India constructs the deepest diaphragm wall element](/storage/2023/10/bauer-india-constructs-the-deepest-diaphragm-wall-element-653e584febe60.jpg)
Perforation
04/11/2023
Bauer India constructs the deepest diaphragm wall element
Bauer India constructs the deepest diaphragm wall element du...
![Klemm Bohrtechnik GmbH celebrates double anniversary](/storage/2023/10/klemm-bohrtechnik-gmbh-celebrates-double-anniversary-6533bbdb9ca06.jpg)
Perforation
27/10/2023
Klemm Bohrtechnik GmbH celebrates double anniversary
This year, Klemm Bohrtechnik GmbH is celebrating two anniver...
![Brownfield Remediation from A to Z on Berlin Airport Grounds](/storage/2023/09/brownfield-remediation-from-a-to-z-on-berlin-airport-grounds-650d904012be8.jpg)
Perforation
26/09/2023
Brownfield Remediation from A to Z on Berlin Airport Grounds
Alongside the operations building, they also needed to disma...
![Bauer Spezialtiefbau executes foundation works for the world’s largest monopile manufacturing facility for offshore wind](/storage/2023/08/bauer-spezialtiefbau-executes-foundation-works-for-the-worlds-largest-monopile-manufacturing-facility-for-offshore-wind-64e0b38f3aef3.png)
Perforation
30/08/2023
Bauer Spezialtiefbau executes foundation works for the world’s largest monopile manufacturing facility for offshore wind
SeAH Wind Ltd. commissioned the Joint Venture between Bauer...
Altri International
![100,000th machine: Liebherr sets milestone on its 75th anniversary](/storage/2024/07/100000th-machine-liebherr-sets-milestone-on-its-75th-anniversary-66a4882ac8547.jpg)
International
29/07/2024
100,000th machine: Liebherr sets milestone on its 75th anniversary
It is another milestone in the historyLiebherr-Hydraulikbagg...
![KönningKrane takes delivery of Liebherr LTM 1160-5.2](/storage/2024/07/konningkrane-takes-delivery-of-liebherr-ltm-1160-52-669f9a5f379f9.jpg)
International
29/07/2024
KönningKrane takes delivery of Liebherr LTM 1160-5.2
KönningKrane GmbH & Co KG from Stadtlohn in the north-west o...
![Exclusive new Cat Track Wear Sensor](/storage/2024/07/exclusive-new-cat-track-wear-sensor-669f9e20ae70c.jpg)
International
26/07/2024
Exclusive new Cat Track Wear Sensor
Exclusive new Cat Track Wear Sensor provides remote, no-touc...
![Tamás és Zsolt Kft. took delivery of Liebherr LTM 1650-8.1](/storage/2024/07/tamas-es-zsolt-kft-took-delivery-of-liebherr-ltm-1650-81-6688f18bdc18d.jpg)
International
26/07/2024
Tamás és Zsolt Kft. took delivery of Liebherr LTM 1650-8.1
Tamás és Zsolt Kft. has added a Liebherr LTM 1650-8.1 to its...
![Cummins opens new powertrain test facility](/storage/2024/07/cummins-opens-new-powertrain-test-facility-669f9c6a4b904.jpg)
International
25/07/2024
Cummins opens new powertrain test facility
Cummins has opened a new powertrain test facility to support...
![Grove GMK6300L-1 proves perfect for compact jobsite in Rotterdam](/storage/2024/07/grove-gmk6300l-1-proves-perfect-for-compact-jobsite-in-rotterdam-6683b901e94d4.jpg)
International
25/07/2024
Grove GMK6300L-1 proves perfect for compact jobsite in Rotterdam
Kraanverhuur Boekestijn sent its Grove GMK6300L-1 for city c...