Home \ International \ Bauer Spezialtiefbau completes follow-up order on the Monte Grande dam
Bauer Spezialtiefbau completes follow-up order on the Monte Grande dam
11/07/2023
Pubblicato da Ettore Zanatta
Bauer Fundaciones Dominicana S.R.L., the Dominican subsidiary of Bauer Spezialtiefbau GmbH, was commissioned in 2019 to construct a cut-off wall to seal off the dam base.
The Monte Grande dam in the southwest of the Dominican Republic serves as a key element of the country’s infrastructure – for controlling the Yaque del Sur River's water level, flood protection and generation of electrical energy. Tourism and using dammed water for irrigation of agricultural land also play a significant role.
Bauer Fundaciones Dominicana S.R.L., the Dominican subsidiary of Bauer Spezialtiefbau GmbH, was commissioned in 2019 to construct a cut-off wall to seal off the dam base. By May 2020, Bauer constructed around 26,000 m² of cut-off wall over a length of 1,350 m, down to an average depth of 23 m and with a thickness of 800 mm underneath the dam foundations. In May 2022, Bauer returned to the Monte Grande dam for Phase II which consisted of the construction of a reinforced diaphragm wall acting as a flip lip for the dam spillway, protecting the toe of the dam from erosion.
In total, 55 panels were installed with a thickness of 800 mm. Panel lengths varied between 2.8 m for a single-bite panel up to 7.1 m for a triple-bite panel. A Bauer polymer-based stabilizing slurry was used to assist the excavation work with two rope grabs. Depending on the requirements, different panel shapes were constructed including straight panels as well as L- and V-shaped panels. “In total, we constructed 7,828 m² of diaphragm wall with a total length of more than 320 m. The excavation depth was 24.5 m. Temporary flat steel stop-ends with installed water-bar made of rubber were used, followed by reinforcement cages of up to 15 t per panel. Highly fluid (high slump flowable) concrete was used as the filling material,” remarks Project Manager Nuno Pires.
One particular challenge during this project was the excavation of the existing hard soil and rock layers. The geology encountered was very heterogeneous and the strength of rock, particularly the limestone and sandstone, was very high with values up to 45 MPa. To enable the excavation of the panels with rope grabs, pre-drilling was carried out in some cases. This made it possible to relax the strength of the rock and minimize wear and tear on the grabs as far as possible. Project Manager Nuno Pires sums it up enthusiastically: “We are very proud of our fantastic team. The work executed by Bauer was successfully completed in March 2023.”
Ultime notizie di Bauer Macchine Italia
Perforation
30/09/2024
Bauer Spezialtiefbau modernizes John Hart Dam in Canada
Improvement of downstream public safety and facility reliabi...
Perforation
18/07/2024
Bauer secures port project in Scottish town of Ardersier
Bauer constructs diaphragm walls up to 42 m deep and anchor...
Perforation
05/12/2023
Bauer relies on full e-power during Dutch infrastructure project
Innovative electric drill rig from Klemm in operation for th...
Perforation
04/11/2023
Bauer India constructs the deepest diaphragm wall element
Bauer India constructs the deepest diaphragm wall element du...
Perforation
27/10/2023
Klemm Bohrtechnik GmbH celebrates double anniversary
This year, Klemm Bohrtechnik GmbH is celebrating two anniver...
Perforation
26/09/2023
Brownfield Remediation from A to Z on Berlin Airport Grounds
Alongside the operations building, they also needed to disma...
Altri International
International
21/11/2024
Kleemann: New compact crusher used for recycling
Impact crusher MOBIREX MR 100i NEO impresses during operatio...
International
21/11/2024
SITECH partners with Royal Engineers to create poppy and demonstrate tech offering
The demostration involved creating a ground-level poppy desi...
International
20/11/2024
Strong and stable RA30 trucks carry the weight at New Caledonian mine
Three Rokbak RA30 trucks are delivering exceptional durabili...
International
20/11/2024
Tadano AC 7.450-1 Performs Double Duty in Wisconsin
A cost-saving and versatile solution was already on site - a...
International
19/11/2024
Liebherr Tower Cranes and John Paul Construction celebrate 50 years of partnership
Irish construction company John Paul Construction is celebra...
International
18/11/2024
The CMC i23 aerial platform: an example of high performances
CMC i23 is designed to maximise operational efficiency in al...