Home \ International \ Bauer Spezialtiefbau constructs excavation pit for office building in Munich
Bauer Spezialtiefbau constructs excavation pit for office building in Munich
17/12/2021
Pubblicato da Ettore Zanatta
Bauer Spezialtiefbau GmbH was commissioned by Argenta Internationale Anlagegesellschaft & Co. Grundbesitzgesellschaft OHG with the construction of the excavation pit including dewatering.
In the Parkstadt Schwabing neighborhood in the north of Munich, a new office building is currently being constructed on a 13,000 m2 site. For the project “Parkstadt Schwabing, MK3, Office Building Construction”, Bauer Spezialtiefbau GmbH was commissioned by Argenta Internationale Anlagegesellschaft & Co. Grundbesitzgesellschaft OHG with the construction of the excavation pit including dewatering.
For the 9 m deep excavation pit, Bauer is constructing a 6,000 m² single-anchored mixed-in-place cut-off wall (MIP) with a thickness of 550 mm and embedded double U king piles up to a depth of 17 m. Moreover, 750 m² of sheet pile wall are being installed with a maximum depth of 16 m for dewatering. After sufficient uplift prevention has been achieved for the structure, the sheet pile wall will then be pulled out again. In addition, 3,000 running meters of anchors are being installed.
Due to impermeable tertiary layers in the area of the excavation base, depth drainage was used. This requires high logistics efforts and precise coordination with earthworks. Due to large soakaways in the public ground, it is also necessary to pivot the anchor in the MIP wall and increase the anchor distances, which means that staggered anchors with a load of up to 1,800 KN are being used.
Because the level of the impermeable tertiary layer fluctuates widely throughout the site, the retaining wall is also being constructed with a final depth that varies by up to 5 m. “With our MIP method, we are able to vary the drilling depth as needed or adapt to the soil conditions. This offers us a major advantage compared to sheet pile walls, which were originally planned, since the lengths of the sheet pile wall have to be defined and ordered in advance,” explains Bauer Project Manager Michael Doll.
An RG 27 and an RG 19 pile driver from RTG Rammtechnik GmbH are being used, respectively, for the construction of the MIP wall and the sheet pile walls, and a Klemm KR 806 rig is executing the anchor work.
Bauer started works in May this year. The dewatering system and dismantling of the anchors and sheet pile walls is expected to be completed by early 2022. The completion of the office building is planned for 2024.
![](/storage/aziende/14849901962775.jpg)
Ultime notizie di Bauer Macchine Italia
Perforation
18/07/2024
Bauer secures port project in Scottish town of Ardersier
Bauer constructs diaphragm walls up to 42 m deep and anchor...
![Bauer relies on full e-power during Dutch infrastructure project](/storage/2023/12/bauer-relies-on-full-e-power-during-dutch-infrastructure-project-656dc6f86eda6.jpg)
Perforation
05/12/2023
Bauer relies on full e-power during Dutch infrastructure project
Innovative electric drill rig from Klemm in operation for th...
![Bauer India constructs the deepest diaphragm wall element](/storage/2023/10/bauer-india-constructs-the-deepest-diaphragm-wall-element-653e584febe60.jpg)
Perforation
04/11/2023
Bauer India constructs the deepest diaphragm wall element
Bauer India constructs the deepest diaphragm wall element du...
![Klemm Bohrtechnik GmbH celebrates double anniversary](/storage/2023/10/klemm-bohrtechnik-gmbh-celebrates-double-anniversary-6533bbdb9ca06.jpg)
Perforation
27/10/2023
Klemm Bohrtechnik GmbH celebrates double anniversary
This year, Klemm Bohrtechnik GmbH is celebrating two anniver...
![Brownfield Remediation from A to Z on Berlin Airport Grounds](/storage/2023/09/brownfield-remediation-from-a-to-z-on-berlin-airport-grounds-650d904012be8.jpg)
Perforation
26/09/2023
Brownfield Remediation from A to Z on Berlin Airport Grounds
Alongside the operations building, they also needed to disma...
![Bauer Spezialtiefbau executes foundation works for the world’s largest monopile manufacturing facility for offshore wind](/storage/2023/08/bauer-spezialtiefbau-executes-foundation-works-for-the-worlds-largest-monopile-manufacturing-facility-for-offshore-wind-64e0b38f3aef3.png)
Perforation
30/08/2023
Bauer Spezialtiefbau executes foundation works for the world’s largest monopile manufacturing facility for offshore wind
SeAH Wind Ltd. commissioned the Joint Venture between Bauer...
Altri International
![100,000th machine: Liebherr sets milestone on its 75th anniversary](/storage/2024/07/100000th-machine-liebherr-sets-milestone-on-its-75th-anniversary-66a4882ac8547.jpg)
International
29/07/2024
100,000th machine: Liebherr sets milestone on its 75th anniversary
It is another milestone in the historyLiebherr-Hydraulikbagg...
![KönningKrane takes delivery of Liebherr LTM 1160-5.2](/storage/2024/07/konningkrane-takes-delivery-of-liebherr-ltm-1160-52-669f9a5f379f9.jpg)
International
29/07/2024
KönningKrane takes delivery of Liebherr LTM 1160-5.2
KönningKrane GmbH & Co KG from Stadtlohn in the north-west o...
![Exclusive new Cat Track Wear Sensor](/storage/2024/07/exclusive-new-cat-track-wear-sensor-669f9e20ae70c.jpg)
International
26/07/2024
Exclusive new Cat Track Wear Sensor
Exclusive new Cat Track Wear Sensor provides remote, no-touc...
![Tamás és Zsolt Kft. took delivery of Liebherr LTM 1650-8.1](/storage/2024/07/tamas-es-zsolt-kft-took-delivery-of-liebherr-ltm-1650-81-6688f18bdc18d.jpg)
International
26/07/2024
Tamás és Zsolt Kft. took delivery of Liebherr LTM 1650-8.1
Tamás és Zsolt Kft. has added a Liebherr LTM 1650-8.1 to its...
![Cummins opens new powertrain test facility](/storage/2024/07/cummins-opens-new-powertrain-test-facility-669f9c6a4b904.jpg)
International
25/07/2024
Cummins opens new powertrain test facility
Cummins has opened a new powertrain test facility to support...
![Grove GMK6300L-1 proves perfect for compact jobsite in Rotterdam](/storage/2024/07/grove-gmk6300l-1-proves-perfect-for-compact-jobsite-in-rotterdam-6683b901e94d4.jpg)
International
25/07/2024
Grove GMK6300L-1 proves perfect for compact jobsite in Rotterdam
Kraanverhuur Boekestijn sent its Grove GMK6300L-1 for city c...