Home \ International \ Bauer Umwelt remediates industrial area for new work-life district in Munich
Bauer Umwelt remediates industrial area for new work-life district in Munich
29/06/2020
Pubblicato da Redazione
The "iCampus" in eastern Munich is currently an impressive example how history and modernity can be successfully combined.
The “iCampus” in eastern Munich is currently an impressive example how history and modernity can be successfully combined. On an area where motorcycles, clothing and dumplings were once manufactured, property developer R&S Realty II GmbH & Co. KG now creates office facilities around a heritage-listed administration building and also redefines productive work with a highly modern building concept.
Focusing on a mix of living, residential and working spaces, iCampus is being created as a new residential/commercial development in the former factory district. Following planned completion in 2024, it will optimally integrate into the infrastructure of the Bavarian capital. In a premium location near the Ostbahnhof railway station and the “Mittlerer Ring” ring road, it also offers excellent transport connections in all directions.
However, before the future business district can be built, the former industrial site required complete remediation. In April 2019, the joint-venture “Baugrube iCampus Rhenania München”, consisting of Bauer Resources GmbH and Bauer Spezialtiefbau GmbH, were contracted to clear the site, which covers an area of 22.500 m2. A lot has happened since then, starting with the demolition and gutting of existing buildings, brownfield remediation and subsequent excavation for the shell construction work. In the process, around 50.000 mÑ of concrete was broken up and almost 125.000 m3 of ground excavated and disposed of, including 140.000 t of contaminated earth and 80.000 t of natural soil. Numerous challenges needed to be mastered during the works: Removing asbestos from a building is not, in itself, an unusual task. However, when the building is a historically listed villa from the 1920s, and when more asbestos is found in the other existing buildings than was originally expected, then the whole process becomes a little more complicated.
“This requires close coordination with the authorities and architectural offices to ensure proper execution,” explains Burç Akker, site manager from the Bauer Umwelt division of Bauer Resources GmbH. In addition to this, the Bauer team had to deal with extremely complex logistics. “The management and coordination of a high volume of waste material and a large number of trucks in an inner city area, not to mention the limited space, was very challenging,” says Erwin Resch, foreman from the Bauer Umwelt division of the Bauer Resources GmbH. But it’s not only the technical and logistical conditions that were challenging, the planned project time of 15 months is also very ambitious. “Especially if a task is to be realized in such a short time, every step needs to be carefully planned and the team needs to be well organized,” explains Jan Uhlig, project manager from the Bauer Umwelt division of the Bauer Resources GmbH. He adds: “Thanks to the excellent cooperation within our team and with all participants the project ran on schedule despite all the challenges, and we expect to complete our work in July.”
Ultime notizie di Bauer Macchine Italia
Perforation
30/09/2024
Bauer Spezialtiefbau modernizes John Hart Dam in Canada
Improvement of downstream public safety and facility reliabi...
Perforation
18/07/2024
Bauer secures port project in Scottish town of Ardersier
Bauer constructs diaphragm walls up to 42 m deep and anchor...
Perforation
05/12/2023
Bauer relies on full e-power during Dutch infrastructure project
Innovative electric drill rig from Klemm in operation for th...
Perforation
04/11/2023
Bauer India constructs the deepest diaphragm wall element
Bauer India constructs the deepest diaphragm wall element du...
Perforation
27/10/2023
Klemm Bohrtechnik GmbH celebrates double anniversary
This year, Klemm Bohrtechnik GmbH is celebrating two anniver...
Perforation
26/09/2023
Brownfield Remediation from A to Z on Berlin Airport Grounds
Alongside the operations building, they also needed to disma...
Altri International
International
26/11/2024
Mota-Engil orders 10 Liebherr railroad excavators for a major project in West Africa
The Portuguese construction company Mota-Engil has once agai...
International
25/11/2024
New Grove GMK3060L-1 drives busy schedule for Mann Crane Hire
• Mann Crane Hire selected the GMK3060L-1 for its class-lead...
International
25/11/2024
Prinoth Unveils Expanded Production Facility in Granby, Canada
Prinoth held an event to announce the official opening of it...
International
23/11/2024
GPMat International takes delivery of two Raimondi T147s residential development in the South of France
- Official agent of France expands its product lineup with t...
International
22/11/2024
Sarens acquires additional SCHEUERLE SPMT K24 modules
renowned for its expertise in crane rental services, heavy l...
International
22/11/2024
Five WOLFF cranes modernize Oslo’s Ulven district
With a total of five WOLFF cranes of type 7534.16 Clear, Wol...