Home \ International \ Construction site turned upside down
Construction site turned upside down
30/03/2020
Pubblicato da Redazione
Underground construction method at the Thomas-Wimmer-RIng in Munich
With approx. 390,000 commuters, the Bavarian capital is Germany’s top commuter city. The results are growing congestion, overcrowded trains, and a shortage of parking areas. To counteract the extreme lack of parking, an underground parking garage is being constructed right under the Altstadtring, at the eastern part of the ring road in the center of Munich, between Isartor and Maximilianstraße. Dimensions: 140 m long, 30-45 m wide, 13 m deep.
To ensure continued traffic flow on two lanes during the construction phase and let 25,000 cars pass by the site with as little congestion as possible, the site has been divided up into two sections: East and West. The resulting two, extremely narrow sites within confined areas make for a real challenge. Bauer Umwelt, the environmental business division of Bauer Resources GmbH, was tasked with the excavation of both building pits. But before excavation could begin, Bauer Spezialtiefbau GmbH erected a pile wall with a diameter of 88 cm. The wall acts as a protective structure for the excavation pit and is also the protective outer shell of the future underground garage.
In November 2017, excavation of the pit on the eastern side – with a volume of 40,000 m3 and a depth of up to 13 m – finally commenced. After completion of the eastern construction section in 2018, work on the western area began in the spring of 2019. But everything is different with this section, the site is literally turned upside down. The reason: The foundations of the adjacent neighboring building are too close to the excavation pit, and a tie back of the pile wall that would anchor it to the ground is not possible. Therefore, an underground construction method is used whereby the first lower level is mounted to the pile wall, so the shell is created from the top down.
“The capping beam of the first lower level with an area of around 2,700 m2 and consisting of six concrete sections was completed over the winter months. Now the excavation can be done underground,” explains Christian Heinig, foreman at the environmental business division Bauer Umwelt of Bauer Resources GmbH. Using a mini digger, a tunnel construction digger and a caterpillar, a total of 18,000 m3 of soil are brought to the surface. The entire soil excavation in the west amounts to approx. 28,000 m3. The cramped spatial conditions are of particular difficulty in the mining method. In some sections, the room height is just 4 m and only five employees can work here at the same time. “That’s why the planning and implementation of the underground excavation in the western section is regarded as one of the most spectacular building projects in Germany,” according to Thomas Reinthaler, Sales Manager for the south region of Bauer Umwelt, the environmental business division of Bauer Resources GmbH.
The work executed by Bauer is expected to be completed according to schedule by September 2020. From spring 2021, 520 vehicles will be able to find a parking space on three levels.
Ultime notizie di Bauer Macchine Italia
Perforation
30/09/2024
Bauer Spezialtiefbau modernizes John Hart Dam in Canada
Improvement of downstream public safety and facility reliabi...
Perforation
18/07/2024
Bauer secures port project in Scottish town of Ardersier
Bauer constructs diaphragm walls up to 42 m deep and anchor...
Perforation
05/12/2023
Bauer relies on full e-power during Dutch infrastructure project
Innovative electric drill rig from Klemm in operation for th...
Perforation
04/11/2023
Bauer India constructs the deepest diaphragm wall element
Bauer India constructs the deepest diaphragm wall element du...
Perforation
27/10/2023
Klemm Bohrtechnik GmbH celebrates double anniversary
This year, Klemm Bohrtechnik GmbH is celebrating two anniver...
Perforation
26/09/2023
Brownfield Remediation from A to Z on Berlin Airport Grounds
Alongside the operations building, they also needed to disma...
Altri International
International
25/11/2024
New Grove GMK3060L-1 drives busy schedule for Mann Crane Hire
• Mann Crane Hire selected the GMK3060L-1 for its class-lead...
International
25/11/2024
Prinoth Unveils Expanded Production Facility in Granby, Canada
Prinoth held an event to announce the official opening of it...
International
23/11/2024
GPMat International takes delivery of two Raimondi T147s residential development in the South of France
- Official agent of France expands its product lineup with t...
International
22/11/2024
Sarens acquires additional SCHEUERLE SPMT K24 modules
renowned for its expertise in crane rental services, heavy l...
International
22/11/2024
Five WOLFF cranes modernize Oslo’s Ulven district
With a total of five WOLFF cranes of type 7534.16 Clear, Wol...
International
21/11/2024
Kleemann: New compact crusher used for recycling
Impact crusher MOBIREX MR 100i NEO impresses during operatio...