Home \ International \ Herrenknecht: about-turn for "SUSE" in the Filder Tunnel
Herrenknecht: about-turn for "SUSE" in the Filder Tunnel
06/09/2018
Pubblicato da Redazione
In late July the moment has come: tunnel boring machine "SUSE" (Ø 10,820 mm) has completely excavated the western tube of the Filder Tunnel.
In late July the moment has come: tunnel boring machine "SUSE" (Ø 10,820 mm) has completely excavated the western tube of the Filder Tunnel.
Now, in a specially built cavern, the approximately 120 meter long Multi-mode TBM from Herrenknecht is disassembled into individual parts and turned around underground. From the fall of 2018 it is due to commence excavation work in the remaining 3.4 kilometer section of the eastern tube.
"Stuttgart-Ulm schneller erreicht" (Stuttgart-Ulm reached faster) is behind the acronym used to name the Herrenknecht tunnel boring machine "SUSE" (Ø 10,820 mm), which successfully finished its third shield drive in the Baden- Württemberg state capital in late July. With the end of the advance the crew from joint venture ARGE ATCOST 21 (Porr Bau GmbH Tunnelbau, G. Hinteregger & Söhne Baugesellschaft m.b.H., Östu-Stettin Hoch- und Tiefbau GmbH, Swietelsky Baugesellschaft m.b.H.) has now completed the western tube of the approximately 9.5 kilometer long twin-tube Filder Tunnel.
For the final project breakthrough, "SUSE" still has to excavate a 3.4 kilometer long section in the eastern tube. The tunnelling work is scheduled to start in the fall of 2018. Prior to that, the approximately 2,000 tonne and 120 meter long TBM will be disassembled into several parts and turned around in a specially built cavern inside the rock mass. "Such an about-turn underground with a TBM of this size is absolutely exceptional," says Dr.-Ing. E. H. Martin Herrenknecht. "This shows what extraordinary technical feats are being achieved during the construction work on the Filder Tunnel. Hats off to the site crew!"
The tunnel section is located in heterogeneous rock strata and overcomes a total height difference of 155 meters with a slope of up to 2.5 percent. Due to the complex project requirements, initially no mechanized tunnelling was planned for the Filder Tunnel. However, the particularly flexible and convertible Multi-mode TBM machine type from Herrenknecht has convinced the client Deutsche Bahn of the advantages of mechanized tunnelling over a large part of the tunnel route.
In the upper section of the Filder Tunnel the convertible Multi-mode TBM "SUSE" worked in EPB mode with screw conveyor muck removal, in the lower Filder Tunnel in open single-shield mode with belt conveyor discharge. The only area the machine was not used was in the geological transition zone, where miners removed the material from the rock using diggers and loosening blasting.
The Filder Tunnel is the longest on the new line between Stuttgart and Ulm, which will link the new central railway station with the Filder Plain. As a result of the railway project, travel times between Stuttgart and Ulm will be almost halved. Around ten million passengers per year will benefit from the scheme. Contractors working on other tunnelling sections of the Stuttgart-Ulm railway project are also relying on Herrenknecht tunnel boring machines.
For example, the two Herrenknecht machines "WANDA" and "Sibylle" (Ø 10,820 mm) are in operation for the Albvorland Tunnel. The EPB Shield "Käthchen" (Ø 11,340 mm) recently completed excavation of the 8.8 kilometer long Bossler Tunnel.
Ultime notizie di Herrenknecht
Perforation
18/09/2024
Herrenknecht returns to the Gotthard
Mechanized tunnelling technology from Schwanau is once again...
Perforation
15/05/2024
Second wind farm with Herrenknecht OFD technology
Herrenknecht's Offshore Foundation Drilling (OFD) technology...
Perforation
18/03/2024
Herrenknecht: eight tunnel boring machines for the Brenner project
Seventh tunnel boring machine handed over for the record-bre...
Perforation
08/02/2024
Herrenknecht presents tunnel boring machine for Vienna
Herrenknecht is supplying a tunnel boring machine for tunnel...
03/05/2021
Advance record at the Brenner Base Tunnel
The miners in the Brenner Base Tunnel are pushing ahead rapi...
23/07/2020
Mighty breakthrough for Europe's biggest boring machine
Following the specifications of customer Pavimental, Herrenk...
Altri International
International
21/11/2024
Kleemann: New compact crusher used for recycling
Impact crusher MOBIREX MR 100i NEO impresses during operatio...
International
21/11/2024
SITECH partners with Royal Engineers to create poppy and demonstrate tech offering
The demostration involved creating a ground-level poppy desi...
International
20/11/2024
Strong and stable RA30 trucks carry the weight at New Caledonian mine
Three Rokbak RA30 trucks are delivering exceptional durabili...
International
20/11/2024
Tadano AC 7.450-1 Performs Double Duty in Wisconsin
A cost-saving and versatile solution was already on site - a...
International
19/11/2024
Liebherr Tower Cranes and John Paul Construction celebrate 50 years of partnership
Irish construction company John Paul Construction is celebra...
International
18/11/2024
The CMC i23 aerial platform: an example of high performances
CMC i23 is designed to maximise operational efficiency in al...