Herrenknecht: about-turn for "SUSE" in the Filder Tunnel
06/09/2018
Pubblicato da Redazione
In late July the moment has come: tunnel boring machine "SUSE" (Ø 10,820 mm) has completely excavated the western tube of the Filder Tunnel.
In late July the moment has come: tunnel boring machine "SUSE" (Ø 10,820 mm) has completely excavated the western tube of the Filder Tunnel.
Now, in a specially built cavern, the approximately 120 meter long Multi-mode TBM from Herrenknecht is disassembled into individual parts and turned around underground. From the fall of 2018 it is due to commence excavation work in the remaining 3.4 kilometer section of the eastern tube.
"Stuttgart-Ulm schneller erreicht" (Stuttgart-Ulm reached faster) is behind the acronym used to name the Herrenknecht tunnel boring machine "SUSE" (Ø 10,820 mm), which successfully finished its third shield drive in the Baden- Württemberg state capital in late July. With the end of the advance the crew from joint venture ARGE ATCOST 21 (Porr Bau GmbH Tunnelbau, G. Hinteregger & Söhne Baugesellschaft m.b.H., Östu-Stettin Hoch- und Tiefbau GmbH, Swietelsky Baugesellschaft m.b.H.) has now completed the western tube of the approximately 9.5 kilometer long twin-tube Filder Tunnel.
For the final project breakthrough, "SUSE" still has to excavate a 3.4 kilometer long section in the eastern tube. The tunnelling work is scheduled to start in the fall of 2018. Prior to that, the approximately 2,000 tonne and 120 meter long TBM will be disassembled into several parts and turned around in a specially built cavern inside the rock mass. "Such an about-turn underground with a TBM of this size is absolutely exceptional," says Dr.-Ing. E. H. Martin Herrenknecht. "This shows what extraordinary technical feats are being achieved during the construction work on the Filder Tunnel. Hats off to the site crew!"
The tunnel section is located in heterogeneous rock strata and overcomes a total height difference of 155 meters with a slope of up to 2.5 percent. Due to the complex project requirements, initially no mechanized tunnelling was planned for the Filder Tunnel. However, the particularly flexible and convertible Multi-mode TBM machine type from Herrenknecht has convinced the client Deutsche Bahn of the advantages of mechanized tunnelling over a large part of the tunnel route.
In the upper section of the Filder Tunnel the convertible Multi-mode TBM "SUSE" worked in EPB mode with screw conveyor muck removal, in the lower Filder Tunnel in open single-shield mode with belt conveyor discharge. The only area the machine was not used was in the geological transition zone, where miners removed the material from the rock using diggers and loosening blasting.
The Filder Tunnel is the longest on the new line between Stuttgart and Ulm, which will link the new central railway station with the Filder Plain. As a result of the railway project, travel times between Stuttgart and Ulm will be almost halved. Around ten million passengers per year will benefit from the scheme. Contractors working on other tunnelling sections of the Stuttgart-Ulm railway project are also relying on Herrenknecht tunnel boring machines.
For example, the two Herrenknecht machines "WANDA" and "Sibylle" (Ø 10,820 mm) are in operation for the Albvorland Tunnel. The EPB Shield "Käthchen" (Ø 11,340 mm) recently completed excavation of the 8.8 kilometer long Bossler Tunnel.
![](/storage/aziende/14851858047381.jpg)
Ultime notizie di Herrenknecht
![Second wind farm with Herrenknecht OFD technology](/storage/2024/05/second-wind-farm-with-herrenknecht-ofd-technology-663cc3d548181.jpg)
Perforation
15/05/2024
Second wind farm with Herrenknecht OFD technology
Herrenknecht's Offshore Foundation Drilling (OFD) technology...
![Herrenknecht: eight tunnel boring machines for the Brenner project](/storage/2024/03/herrenknecht-eight-tunnel-boring-machines-for-the-brenner-project-65eb1a0c3fa0c.jpg)
Perforation
18/03/2024
Herrenknecht: eight tunnel boring machines for the Brenner project
Seventh tunnel boring machine handed over for the record-bre...
![Herrenknecht presents tunnel boring machine for Vienna](/storage/2024/02/herrenknecht-presents-tunnel-boring-machine-for-vienna-65bccde7bda20.jpg)
Perforation
08/02/2024
Herrenknecht presents tunnel boring machine for Vienna
Herrenknecht is supplying a tunnel boring machine for tunnel...
![Advance record at the Brenner Base Tunnel](/storage/old/nc6001480/1619950865885.jpeg)
03/05/2021
Advance record at the Brenner Base Tunnel
The miners in the Brenner Base Tunnel are pushing ahead rapi...
![Mighty breakthrough for Europe's biggest boring machine](/storage/old/nc6001254/15951384712299.jpeg)
23/07/2020
Mighty breakthrough for Europe's biggest boring machine
Following the specifications of customer Pavimental, Herrenk...
![Herrenknecht: Suse, Sibylle, Wanda and Käthchen from Baden set a fast pace in Swabia](/storage/old/nc6001099/15789303995252.jpeg)
17/01/2020
Herrenknecht: Suse, Sibylle, Wanda and Käthchen from Baden set a fast pace in Swabia
Mechanized tunnelling technology for efficient and environme...
Altri International
![Liebherr's mobile crane lifts construction crane over treetops](/storage/2024/06/liebherrs-mobile-crane-lifts-construction-crane-over-treetops-66813cf080556.jpg)
International
16/07/2024
Liebherr's mobile crane lifts construction crane over treetops
LTM 1130-5.1 lifts Liebherr 28 K construction crane out of s...
![Kohler Energy Publishes a Market-First Environmental Declaration for a Mission-Critical Generating Set](/storage/2024/06/kohler-energy-publishes-a-market-first-environmental-declaration-for-a-mission-critical-generating-set-66813adfe1ca1.jpg)
International
16/07/2024
Kohler Energy Publishes a Market-First Environmental Declaration for a Mission-Critical Generating Set
Independently verified document provides complete visibility...
![Two Grove cranes from Palumbo Heavy Lift team up for spectacular tandem lifts in Naples](/storage/2024/06/two-grove-cranes-from-palumbo-heavy-lift-team-up-for-spectacular-tandem-lifts-in-naples-668133f2109e4.jpg)
International
15/07/2024
Two Grove cranes from Palumbo Heavy Lift team up for spectacular tandem lifts in Naples
Palumbo Heavy Lift sent its new Grove GMK5250XL-1 plus its G...
![Liebherr MK 140 Secures Saint-Maurice Cathedral](/storage/2024/06/liebherr-mk-140-secures-saint-maurice-cathedral-668115418ed35.jpg)
International
12/07/2024
Liebherr MK 140 Secures Saint-Maurice Cathedral
A Liebherr MK 140 mobile construction crane was instrumental...
![New Tadano AC 5.220-1 all terrain crane for Safar](/storage/2024/07/new-tadano-ac-5220-1-all-terrain-crane-for-safar-6682588d6e0ed.jpg)
International
11/07/2024
New Tadano AC 5.220-1 all terrain crane for Safar
Safar ordered the AC 5.220-1 with a heavy-duty short jib and...
![Liebherr's XPower wheel loaders are ideal for handling sand and gravel](/storage/2024/06/liebherrs-xpower-wheel-loaders-are-ideal-for-handling-sand-and-gravel-668115fe30a33.jpg)
International
11/07/2024
Liebherr's XPower wheel loaders are ideal for handling sand and gravel
Liebherr's XPower wheel loaders and their smart machine conc...