Herrenknecht hard rock TBM "Ulrikke" takes tunnelling in Norway
03/01/2018
Pubblicato da Redazione
Herrenknecht hard rock TBM "Ulrikke" takes tunnelling in Norway
Whether it's a world record with the longest railway tunnel on earth at the Brenner or the epoch-making Gotthard project: the business of mechanized tunnel boring through hard rock is currently reaching new heights in Europe.
Now Scandinavia is discovering the advantages of mechanized tunnelling. With the breakthrough at the Ulriken Tunnel, the first major tunnel project in Norway using a Herrenknecht Gripper TBM has been successfully completed.
Hard, harder, Norwegian gneiss
With compressive strength of up to 300 megapascals, Scandinavian rock is regarded worldwide as the ultimate test of mechanized tunnelling technology. International construction companies trust in Herrenknecht's technology for this complex challenge. The global market leader from Schwanau looks back at decades of experience in tunnelling through the toughest of hard rock: Herrenknecht hard rock machines have excavated around 820 kilometers of tunnels in more than 200 projects since the year 2000. In late August the breakthrough of the Ulriken Tunnel for the expansion of the Norwegian railway network added another hard rock highlight to the list.
The railway tunnel through the Ulriken mountain is the first major traffic project in Norway to be realized with a Gripper TBM. On the west coast of Norway, the hard rock machine “Ulrikke” (Ø 9,300 mm) has bitten its way through extremely tough rock meter by meter in recent months. The miners of the “Skanska Strabag Ulriken ANS” joint-venture have driven the 6.9 kilometer long tunnel between the cities of Bergen and Arna with excellent top advance rates of up to 170 meters per week.
Drill & blast tunneling
In Norway, drill & blast tunnelling traditionally dominates: "The realization that mechanical tunnelling is a real alternative even in the extremely hard rock now seems to be spreading in Scandinavia", says Eric Fourchault, Project Manager at Herrenknecht. Compared to traditional drill & blast, mechanized tunnelling has a number of advantages. It has less impact on the mountain and provides highest safety for the crew, without the shocks of blasting. The short distance of only 30 meters from the existing operational railway tunnel was therefore decisive for the use of a TBM at the Ulriken Tunnel. Furthermore, machine technology can achieve higher average advance rates, especially over long distances.
TBMs are already being preferred over the traditional drill & blast method in other Norwegian tunnel porjects. For Norway's latest large-scale infrastructure project, the “Follo Line” in Oslo, four Double Shield TBMs (Ø 9,900 mm) from Herrenknecht are creating the country's longest railway tunnel. In 15 months of excavation, more than 19 kilometers of the approximately 38 kilometer long total route have meanwhile been driven as a tunnel.
Ultime notizie di Herrenknecht
Perforation
15/05/2024
Second wind farm with Herrenknecht OFD technology
Herrenknecht's Offshore Foundation Drilling (OFD) technology...
Perforation
18/03/2024
Herrenknecht: eight tunnel boring machines for the Brenner project
Seventh tunnel boring machine handed over for the record-bre...
Perforation
08/02/2024
Herrenknecht presents tunnel boring machine for Vienna
Herrenknecht is supplying a tunnel boring machine for tunnel...
03/05/2021
Advance record at the Brenner Base Tunnel
The miners in the Brenner Base Tunnel are pushing ahead rapi...
23/07/2020
Mighty breakthrough for Europe's biggest boring machine
Following the specifications of customer Pavimental, Herrenk...
17/01/2020
Herrenknecht: Suse, Sibylle, Wanda and Käthchen from Baden set a fast pace in Swabia
Mechanized tunnelling technology for efficient and environme...
Altri International
International
16/07/2024
Liebherr's mobile crane lifts construction crane over treetops
LTM 1130-5.1 lifts Liebherr 28 K construction crane out of s...
International
16/07/2024
Kohler Energy Publishes a Market-First Environmental Declaration for a Mission-Critical Generating Set
Independently verified document provides complete visibility...
International
15/07/2024
Two Grove cranes from Palumbo Heavy Lift team up for spectacular tandem lifts in Naples
Palumbo Heavy Lift sent its new Grove GMK5250XL-1 plus its G...
International
12/07/2024
Liebherr MK 140 Secures Saint-Maurice Cathedral
A Liebherr MK 140 mobile construction crane was instrumental...
International
11/07/2024
New Tadano AC 5.220-1 all terrain crane for Safar
Safar ordered the AC 5.220-1 with a heavy-duty short jib and...
International
11/07/2024
Liebherr's XPower wheel loaders are ideal for handling sand and gravel
Liebherr's XPower wheel loaders and their smart machine conc...