B&G Crane Service LLC utilized a 300-ton capacity Hydra-Slide HT300 heavy-track hydraulic skidding system and other equipment to remove and replace two heat exchanger units for a project in Calcasieu, Louisiana
B&G Crane Service LLC utilized a 300-ton capacity Hydra-Slide HT300 heavy-track hydraulic skidding system and other equipment to remove and replace two heat exchanger units for a project in Calcasieu, Louisiana recently.
The full scope of work included removal and replacement of five exchangers; two were atop a 51 ft.-high structure elevation and removed by crane, while the smallest unit was moved using skates. The HT300 was used to slide the old exchangers, weighing 49,000 lbs. and 59,000 lbs., a distance of 60 ft. before repeating the process in reverse with the replacement units that weighed 58,000 lbs. and 66,000 lbs.
The standard HT300 package comes complete with load-bearing track, four skid shoes, push cylinders and all connecting hardware. The load-moving solution needs minimal clearance and has a total height of only 7 in. (180mm). Additional skid track sections were supplied by Hydra-Slide on short notice to extend the 50 ft. of double track that B&G had available. They connect with a simple lug and pin set and could have been leap-frogged to slide longer distances, if a requirement arose.
The equipment combined with other lifting technologies, including two Liebherr mobile cranes—a 100t capacity five-axle LTM 1100-5.2 and a 500t capacity eight-axle LTM 1500-8.1. B&G also utilized a J&R Engineering Lift-n-Lock 1400 series hydraulic gantry and two Scheurle self-propelled modular transporters (SPMT), of six and 12 lines respectively.
Mark Morris, rigging superintendent at B&G Crane, explained that the first stage of the project was removal of the existing exchangers using the LTM 1500-8.1. He added: “At that point, grating from the elevation was opened up to allow rigging to be lowered through the existing floor. The exchangers were then blocked up with cribbing to allow installation of the Hydra-Slide tracks before they were lowered onto the skid shoes.”
Once the exchangers had been skidded clear of the site, the LTM 1100-5.2 lifted them onto the SPMTs, for transportation to a lay-down area. Morris said: “The process was completed in four, 12-hour shifts, which included all the required rigging, setup, removal and installation work”.
Extra safety measures were implemented in the planning stages to allow for elevated work on false work platforms, which were essentially barge ramps created by fabricating hand rails to OSHA specifications. Morris explained that the solution prevented potential fall and drop-related accidents from height.
“The safety mantra on the project aligned well with the Hydra-Slide equipment”, Morris continued. “Safe and controlled movement of the loads on the elevated platforms not only provides for smooth operation and minimal labor intensity, but also gives clients added confidence in our execution of work. We have used the Hydra Slide equipment on several projects over the last four years since I have been with the company and I look forward to applying it on many more”.
Ultime notizie di
01/07/2021
The compact Sennebogen 613 E telescopic mobile crane proves its flexibility and safety in the mine
Südwestdeutsche Salzwerke AG welcomed a new Sennebogen 613 E...
07/11/2019
COMANSA presents its new 21LC1400 model
A new large-capacity Flat-Top crane
26/09/2017
Robbins Slurry TBM ramps up for Mumbai Metro Line 3
The first of two Slurry TBMs, a rebuilt 6.65 m (21.8 ft) dia...
23/09/2017
The world’s strongest rope for the German Zugspitzbahn
For walkers and winter visitors, there are two ways to ride...
21/09/2017
Modulift beams suspend full scale model fighter jet
Four Modulift spreader beams were used to suspend a full sca...
20/09/2017
A tunnel project with PSC Crane & Rigging
PSC Crane & Rigging, headquartered in Piqua, Ohio, supplied...
Altri International
International
23/11/2024
GPMat International takes delivery of two Raimondi T147s residential development in the South of France
- Official agent of France expands its product lineup with t...
International
22/11/2024
Sarens acquires additional SCHEUERLE SPMT K24 modules
renowned for its expertise in crane rental services, heavy l...
International
22/11/2024
Five WOLFF cranes modernize Oslo’s Ulven district
With a total of five WOLFF cranes of type 7534.16 Clear, Wol...
International
21/11/2024
Kleemann: New compact crusher used for recycling
Impact crusher MOBIREX MR 100i NEO impresses during operatio...
International
21/11/2024
SITECH partners with Royal Engineers to create poppy and demonstrate tech offering
The demostration involved creating a ground-level poppy desi...
International
20/11/2024
Strong and stable RA30 trucks carry the weight at New Caledonian mine
Three Rokbak RA30 trucks are delivering exceptional durabili...