Home \ International \ That’s a Wrap for Robbins Rock Machine ‘Driller Mike’
That’s a Wrap for Robbins Rock Machine ‘Driller Mike’
26/10/2018
Pubblicato da Redazione
Tough TBM and Team overcome the odds with Atlanta breakthrough
On October 4, 2018, onlookers watched as a 3.8 m (12.5 ft) diameter Robbins Main Beam TBM completed its epic journey. The TBM, christened “Driller Mike”, after local rapper and activist “Killer Mike”, overcame extremely hard rock conditions along a curving 8.0 km (5.0 mi) tunnel to bolster the city of Atlanta, Georgia, USA’s water supply.
The new tunnel brings the Atlanta Water Supply Program one step closer to increasing the city’s water capacity to between 30 and 90 days depending on daily usage. “Our schedule for the project was very aggressive but the project team stayed together to overcome issues related to the mining of the tunnel,” said Bob Huie, Project Director for the PC Russell JV, the Construction Manager at Risk (CMAR) for the project.
The unique structure of the project team is credited with the overall project success despite challenges. “I’m proud of our team. They had obstacles and challenges and challenging ground, but they stuck together and didn’t give up, and they were successful. There was great leadership and supervision all around,” said Larry Weslowski, Tunnel Superintendent for the PC Russell JV.
The project is only the third such large construction project in the U.S. to use the CMAR structure. The PC Construction/HJ Russell JV was selected as the CMAR for the project, who then purchased the Robbins Main Beam TBM for the tunnel. The designer for the construction works including tunnel and shafts, JP2—consisting of Stantec, PRAD Group, Inc., and River 2 Tap—specified the hard rock TBM. Operation and assembly of the TBM was then sub-contracted to the Atkinson/Technique JV.
The robust TBM was assembled using Onsite First Time Assembly (OFTA) at the massive Bellwood Quarry site with help from Robbins personnel. “The guys built everything per the specs to help with scheduling. It was a challenge but there was no negativity during the process,” said Weslowski. Despite summer temperatures hitting 43 degrees Celsius (110 degrees Fahrenheit) and 100 percent humidity, the TBM was ready to launch by October 2016.
Hard granitic rock challenged the 19-inch disc cutters from the outset. “There was ground so hard that it would take eight hours to go 1.5 m (5 ft). It was between 117 and 310 MPa (17,000 and 45,000 psi) UCS. The beginning of the job was tough,” said Weslowski, but he added that once the learning curve had been overcome “they started breaking project records left and right towards the end. We got a best day of 38.4 m (126 ft). Rates just kept increasing.”
Other challenges included groundwater encountered during tunneling. “We did encounter groundwater contamination that required remediation. This remediation work was completed successfully,” said Huie.
With tunneling complete, the USD $300 million project for the City of Atlanta’s Department of Watershed Management is on track to meet its scheduled overall completion date of September 2019. The project will turn the inactive Bellwood quarry into a 9.1 billion liter (2.4 billion gallon) raw water storage facility connecting with the Chattahoochee River and various water treatment facilities.
Ultime notizie di OnSite News
Lifting
22/07/2024
Northbank Civil and Marine Purchases Tadano GTC-1600
Northbank Civil and Marine, a heavy civil, marine, and indus...
Earthmoving Machinery
19/07/2024
Rokbak partners with HMD to strengthen presence in West Africa
Construction, quarrying and mining companies in West Africa...
Lifting
19/07/2024
More reach, strength, and flexibility with new Grove rough-terrain cranes
Grove GRT765 and GRT780 were presented to customers at the M...
Lifting
17/07/2024
Sinoboom TB58RJ Plus telescopic boom lift reaches Australia
The tallest model in the Sinoboom range of diesel-powered te...
Lifting
11/07/2024
New Tadano AC 5.220-1 all terrain crane for Safar
Safar ordered the AC 5.220-1 with a heavy-duty short jib and...
Earthmoving Machinery
09/07/2024
Power China calls on Linnhoff asphalt mixing plant to improve rural Kenyan roads
• The Linnhoff TSD1500’s high-mobility design features four...
Altri International
International
29/07/2024
100,000th machine: Liebherr sets milestone on its 75th anniversary
It is another milestone in the historyLiebherr-Hydraulikbagg...
International
29/07/2024
KönningKrane takes delivery of Liebherr LTM 1160-5.2
KönningKrane GmbH & Co KG from Stadtlohn in the north-west o...
International
26/07/2024
Exclusive new Cat Track Wear Sensor
Exclusive new Cat Track Wear Sensor provides remote, no-touc...
International
26/07/2024
Tamás és Zsolt Kft. took delivery of Liebherr LTM 1650-8.1
Tamás és Zsolt Kft. has added a Liebherr LTM 1650-8.1 to its...
International
25/07/2024
Cummins opens new powertrain test facility
Cummins has opened a new powertrain test facility to support...
International
25/07/2024
Grove GMK6300L-1 proves perfect for compact jobsite in Rotterdam
Kraanverhuur Boekestijn sent its Grove GMK6300L-1 for city c...