Home \ International \ The new 100-U.S.-ton class Terex RT 100US outlifts 130-u.s.-ton crane on wind turbine pedestal base construction project
The new 100-U.S.-ton class Terex RT 100US outlifts 130-u.s.-ton crane on wind turbine pedestal base construction project
21/09/2018
Pubblicato da Redazione
The new 100-U.S.-ton class Terex RT 100US outlifts 130-u.s.-ton crane on wind turbine pedestal base construction project
Lattice boom crawler cranes typically steal the wind-turbine-installation show and with good reason. Decked with their turbine packages, long booms and heavy counterweight, they are the most visible part of the operation, called on to lift turbine components weighing up to 300 U.S. tons (272 tonnes).
As with any show, however, much behind-the-scenes prep work must be completed in advance of wind turbine assembly, and this is left to rugged and versatile rough terrain cranes. Even though this work doesn’t get the accolades – and is seldom noticed by the public – it must be completed quickly, efficiently and on time before the main lifting show can go on.
The venue this time for IEA Constructors, Inc., of Indianapolis, Ind., specialists in wind energy, is the 81-turbine Upstream Wind Energy Center north of Neligh, Neb. The 2.5 MW General Electric wind turbines will produce a total of 202.5 MW of energy, supplying power to the grid for households in Neligh and many of the surrounding communities.
Before one rotation of the 186-ft (56.7-m) long blades, ground preparation, concrete and steel pedestal work must be completed. For Roger Galloway, Crane Assembly/Disassembly director, and Mike Hedrick, crane operator for IEA, this means non-stop work with their rough terrain cranes, placing rebar and steel cages in preparation for concrete pours. Their work serves as the turbine’s foundation, securing these massive structures to the earth and withstanding considerable forces generated by the wind and turning blades.
On a project this size, IEA relies on a fleet of rough terrain cranes to offload trucks and lift steel into place. After operating all models at the jobsite, Hedrick, a 30-year crane operator, quickly noticed a difference in power and performance of the new 100-U.S.-ton (90-tonne) capacity class Terex®
RT 100US crane on rent from Terex Cranes distributor, RTL Equipment, Grimes, Iowa. The differences have him quickly warming up to the new design.
Solid, versatile, powerful
Significant planning and orchestration of moving parts are required to properly construct the turbine’s base. IEA starts by excavating a base area roughly 90 ft (27.4 m) in diameter, and the ground where the crane is working must be stabilized to handle the weight of the crane and its load. “The RT 100US crane has a small footprint, which means less ground prep work and less money spent on site preparation,” says Galloway.
Working under a tight 6-hour window for rebar installation, Hedrick uses the RT 100US crane to place rebar panels used for concrete reinforcement, each weighing up to 7,000 lb (3.2 tonnes). “A typical base construction job requires roughly 25 to 30 picks to place the material,” explains Hedrick. “The Terex crane allows me to efficiently move the rebar panels into place and adjust the boom from 40 to 100 ft (12.2 to 30 m), depending on where they are needed.”
The primary reinforcing base component consists of a 13,000-lb (5.9-tonne) bolt cage, positioned at the center of the rebar and filled with concrete. While the controls allow Hedrick to quickly place the panels, the RT 100US’s newly integrated Demag IC-1 control system also gives him the ability to close the valve and dial-down swing function speed for more precise placement of the heavy bolt cage.
“Bringing together the Terex and Demag crane brands allows us to share and capitalize on the technological innovation of Demag and use it in the RT 100US,” explains Bryce Meier, Regional Business Manager for Terex Cranes. “The IC-1 control system has been designed especially for ease of use in the rough terrain market.” According to Hedrick, the new control system helped him to quickly learn crane operation.
Hedrick positioned the 13,000-lb (5.9-tonne) cage using 104 ft (31.7 m) of main boom at a 72-ft (21.9-m) radius. “We tried using a 130-US-ton (120-tonne) capacity class crane to position the cage, but the RT 100US proved to be a better choice,” explains Galloway.
After positioning all the pedestal steel, IEA’s crane operators move to another tower location to repeat the process. The company has four rough terrain cranes and operators on site for base construction and typically divides duties between rebar placement and finish work once the concrete has cured. Sometimes, however, a dedicated rebar crane receives a call-back to finish off a tower base.
This can mean driving long distances to get back to a different tower. “There is no wasted weight with the new RT100US crane design, and it roads very well fully rigged from one site to the next,” says Galloway. Within 10 minutes of reaching a tower site, it’s ready to get back to work.
According to Hedrick, he has drove the crane several miles to get back to a tower base for finishing. “The crane’s automatic transmission reaches speeds of nearly 20 mph (32.2 kmph), which allows it to quickly move between tower locations,” he says. “When I need some extra torque, I can quickly switch to manual drive to maneuver through mud or difficult terrain.”
On a site like this with multiple operators, each may be asked to run the RT 100US at different times. The new IC-1 control system offers one additional feature that helps to save time for IEA operators. “The control system allows up to three different operator profiles to be preset, so preferences are quickly restored,” says Meier.
With the many design improvements built into the new RT 100US, the crane has proven its worth to Hedrick on the Upstream Wind Energy Center. “This one is a solid crane that offers a great load chart at extended boom length and radius,” he says. Galloway adds, “Hats off to the engineers who listened to customer feedback and worked on the updates. This was probably the harshest set-up and overall operating environments that the crane will face, and it passed with flying colors.”
Ultime notizie di Terex Italia
Lifting
15/05/2023
Level UP with Terex Rough Terrain New TRT 65
Terex Rough Terrain Cranes introduced the TRT 65, the latest...
Lifting
13/05/2022
Scandiuzzi Purchase Two Terex Cranes TRT 80s in Italy
Scandiuzzi Steel Constructions have just completed the purch...
Lifting
23/08/2021
Terex RT 35-1 Crane Destined for Research in Antarctica
Terex RT 35-1 Crane Destined for Research in Antarctica
09/03/2021
Level UP with New Terex Rough Terrain Crane
Terex Cranes introduces its TRT 90—the latest model in the T...
Lifting
23/02/2021
Sixty-Six Terex Rough Terrain cranes ordered by Tecno Gru, Italy
Cranes will begin delivery from April and will complete in f...
28/01/2021
A Demag CC 3800-1 lattice-boom crawler crane at the Vado Ligure power plant
Lifting heavy loads over long distances requires large and p...
Altri International
International
23/11/2024
GPMat International takes delivery of two Raimondi T147s residential development in the South of France
- Official agent of France expands its product lineup with t...
International
22/11/2024
Sarens acquires additional SCHEUERLE SPMT K24 modules
renowned for its expertise in crane rental services, heavy l...
International
22/11/2024
Five WOLFF cranes modernize Oslo’s Ulven district
With a total of five WOLFF cranes of type 7534.16 Clear, Wol...
International
21/11/2024
Kleemann: New compact crusher used for recycling
Impact crusher MOBIREX MR 100i NEO impresses during operatio...
International
21/11/2024
SITECH partners with Royal Engineers to create poppy and demonstrate tech offering
The demostration involved creating a ground-level poppy desi...
International
20/11/2024
Strong and stable RA30 trucks carry the weight at New Caledonian mine
Three Rokbak RA30 trucks are delivering exceptional durabili...